SVTRC's 2005 Arena Improvement Projects


Heavy rains in Fall of 2004 resulted in the North side of the arena flooding, making it unusable for classes for several days at a time. To prevent this problem in the future SVTRC took on a 4 point Arena improvement project:

SVTRC expresses graditude to the corporate donars who provided material for the project:
BNSF Burlington Northern Santa Fe (BNSF) Railroad: for their donation of 150 rail road ties
Rinker Rinker Material's Hydro Conduit: for their donation of 54 feet of reinforced concrete culvert pipe
BNSF Texas Industries, Inc (TXI): for their donation and delivery of 180 tons of arena sand and 80 tons of gravel

SVTRC expresses graditude to the many individuals who volunteered countless hours of labor to execute the project:

  • Joe Thatcher
  • Josh Thatcher
  • Cathleen Thatcher
  • Cody Taylor
  • Mike Nolan
  • Tom Lee
  • Katy Lee
  • Steve Limke
  • Thad Limke
  • Mattie Mofat
  • Dick Robertson
  • Tom Davis
  • Casey Davis
  • DJ Emerson
  • Floyd Hayner
  • Wm Aston
  • Bill Wold
  • Gary Williams
  • Johathan Kennemer
  • David Rubenkoening
  • Tony Garza
  • Mr. Sanches
  • Joe Faust
  • Marlan Gantt



A few pictures before the project got started:

Before North side

Arena North Side -- Before

Before South side

Arena South Side -- Before

Before SW Detail

Before S_Detail
Detail pictures showing some of the erosion on the South side of the Arena

Before West side

Arena West Side -- Before

Before Mounting Ramp

This picture shows the area where the barn roof was to be extended to allow riders to enter the arena from the mounting ramp without getting rained on.



The projects began with the Barn Roof Extension

Extended Roof

In March Boyd Industries (the same company that built the arena) extended the barn roof to join the arena




The project began in ernest by loading, hauling and off loading the rail road ties for the retaining wall extension

RR Tie Stacks

A host of volunteers spent 3 weekends in February loading, trailering, and stacking the 150 RR ties donated by BNSF. The ties weigh between 150 and 200 pounds each, it was quite and effort!




The project continued with the hauling and installation of the drainage conduit

Pipe on Trailer

BackhoeTom

TomCariesPipe

KatieSmooths

In March Hydro Conduit donated 9 sections of 12 inch reinforced concrete pipe. In April, Tom Lee and his daughter Katie and Joe Thatcher installed the pipe. Tom expertly operated a rented backhoe to do the trenching. We also used the backhoe to carry the pipe, which weighed over 500 pounds per section. After burrying the pipe under the northwest corner of the arena Katie operated the rented compactor to repack the sand.




Expanding the Retaining wall was a major effort

SouthWall Deadmen looking west

Southside Deadmen looking East
The internal structure of the South wall has 'deadmen' bracing, which is burried in gravel.
SouthSideAfter

The 140 feet of the Southwall, 3 ties high on East end, 6 ties high on West end

NorthSideAfter

The arena's interior perimeter has a two tie high border. It has a platform covering the drainage pipe intake

WestSideAfter

The 70 foot West side is 3 ties high on North end and 6 ties high on South end. It has an opening for the drainage pipe's discharge

West Wall Looking South

West Wall Looking North
West Wall Looking South West Wall Looking North

South West Corner showing gravel

South Wall Looking East 1
South West Corner showing gravel South Wall Looking East from corner

South Wall Looking East 2

South Wall Looking East 3
South Wall Looking East from 1st down spout South Wall Looking East from 2nd down spout

Over the course of most of the weekends in August, September, October, and November a host of volunteers spent innumerable hours expanding the retaining wall from its original 30 foot length to over two-hundred feet. The effort was muscle intensive involving shovels, pry bars, 10 inch nails, sledge hammers, saws, drills, and carrying the ties (which weight up to two-hundred pounds each).




Replenishing the arena sand

TenYardTruckDumping

In November the first 80 cubic yards of arena sand were delivered using "small" trucks directly into the arena.

hirtyYardTruckDumping

An additional 180 cubic yards of arena sand donated and delivered by TXI using "big" trucks. Trucks too large to dump their load inside the arena.

DeliveredSand

Huge piles of sand were to be spread the day after delivery

MovingSand

SmoothingSand

A bobcat with a 3 cubic yard bucket was skillfully operated by Bud and Gerald of Leatherwood Materials (817-596-8658) moving and spreading the new arena sand (they also backfilled the retaing wall with the gravel donated by TXI.




The End Result

WestSideAfter

The southwest corner of the retaing wall.

Chick here to return to SVTRC home page